Per the agreement between the Lake Dunlap WCID, GBRA, and GVEC, GBRA receives a payment each month from GVEC for the electricity produced by the dam of $28,917 ($347,000 per year) PLUS payment of $0.0360 per kilowatt hour for the electricity the dam produces. The capacity charge offsets a portion of the cost of the equipment and maintenance required to be able to produce electricity.
The last page of each invoice reflects the prior months' numbers since the dam began testing the equipment in September 2023. The dam came online fully on October 31, 2023.
2025
January 9, 2025 Debt Payment Report
2024
January 31, 2024 Report
February 28, 2024 Report
March 31, 2024 Report
April 30, 2024 Report
May 31, 2024 Report
June 30, 2024 Report
July 31, 2024 Report
August 31, 2024 Report
September 30, 2024 Report
October 31, 2024 Report
November 30, 2024 Report
December 31, 2024 Report
2023
December 2023 Report