Per the agreement between the Lake Dunlap WCID, GBRA, and GVEC, GBRA receives a payment each month from GVEC for the electricity produced by the dam of $28,917 ($347,000 per year) PLUS payment of $0.0360 per kilowatt hour for the electricity the dam produces. The capacity charge offsets a portion of the cost of the equipment and maintenance required to be able to produce electricity.
The last page of each invoice reflects the prior months' numbers since the dam began testing the equipment in September 2023. The dam came online fully on October 31, 2023.